Tuesday 5 June 2012

Our Upgraded Guardhouse

Our guardhouse is a status symbol of our Community,the first impression of our Community to our visitors. The pride of our Community. The KRT Committee members work together on  a "Gotong-royong" basis repair, repaint and upgraded it. The following has been done to the guardhouse.

By purchasing the materials/parts (some are contributions by our committee members) and doing the work ourselves, we save about 2/3 of the total cost if compared to the works if carried out by contractors. This was able to achieved by the commitment and cooperation of our committee members.


View TPP2A GUARDHOUSE in a larger map
INFORMATION SIGNAGE A3 sizes printing & lamination of signage contribution by AJK David Teo
Police Contact & our KRT contacts
Visitors Registration Requirement

Renovation Contractors' Registration Requirement
 
You don't comply YOU DO NOT ENTER
ADDITIONAL CCTV CAMERA
Supply & installed by vendor


SIREN & BEACON (For Emergency case of threat to our Security guards by intruders & residents)
Two Sirens & a Beacon is installed by our committee members
Beacon
Siren 1
Siren 2
ADDITIONAL FLUORESCENT LAMPS
Installation by our committee members

Front of guardhouse
Rear of guardhouse
Side (Facing out) of guardhouse
AWNING 
Frame supply,fabrication and installation contribution by AJK Zen Wong. Roofing sheet installed by our committee members.
FRESH COAT OF PAINT
Paints for walls,contributed by AJK David Teo. Painting works completed by our committee members








Expenses for Guardhouse upgrade
Material for Signboard stand
163.50

Material & Tools
864.80

Electrical parts & material
410.20

Labour to prepare visitor carpark site
100.00


1538.5

CCTV camera
  840.00
Supply & install

                2378.50




Sponsor


2 x 20ltr Emulsion Paint
AJK David Teo

Iron works
AJK Zen Wong

Guardhouse door (used)
Resident

Signboard (Used)
LKC Hardware




Est repainting work cost by contractor
RM    800.00
Supply & works
Est Siren,revolving lamp,control panel by contractor
RM 1,000.00
Supply & installation
Est Supply & Install door by contractor
RM    300.00

Est. Signboard by contractor
RM 2,500.00
Supply & Install
Est Wiring & installation of fluorescent lamps by contractor
RM    500.00
Supply & install
Estimated cost I work done by vendor
RM 5,100.00