Community Hall reserve land highlight in red |
In order to raise fund for any building,we need to have at least Temporary Occupancy Land 'TOL' before we can proceed,
We approached Mr Wong Soon Weng, Asst Manager of Sales & Marketing, Plenitude Permai Sdn Bhd for assistance. He and their Project Manager Mr Ngor (Have left Plenitude a couple months ago) was very helpful by giving advice on how to apply for the piece of land.
We went to Selangor land office in Bandar Baru Salak Tinggi to apply TOL for the community hall land. Land office said it would not be difficult for us to obtain the TOL but we required to get consensus from Majlis Perbandaran Sepang.
We wrote to MP Sepang on 8th May 2012 for their consensus for our application.
We received a call from Majlis Perbandaran Sepang that they have approved our request on 18th June 2012 and to collect the approval letter from MP Sepang. As our Secretary was out station at that time, we managed to get the letter on 21st June and proceed straight to Selangor land to proceed with our application. Upon arriving at land office. We were told SELANGOR STATE GOVERNMENT have freeze all Government reserve land applications as at 19th June 2012.
A big blow to us as it's so near yet so far!
Do we stop here? Show these few letters to our residents and say we had tried our best! NO! On 8th August , we wrote to our Prime Minister YAB Dato Sri Najib Tun Razak for assistance.
We received a cc letter date 11th September 2012 En Iskandar Mohd Kaus, Tim Ketua Setiausaha Sulit kepada Perdana Menteri to Datuk Haji Ghani Bin Salleh, Pengarah of Pejabat Pembangunan Persekutuan Negeri Selangor to look into our application.
Now we shall follow up with Datuk Haji Ghani Bin Salleh and keep you posted of the developement.
Updated on progress
ReplyDeletePejabat Pembangunan Persekutuan Negeri Selangor is facing resistance from Selangor State Government in getting the said land to built our community hall.
Will updated any future developement.
Cheers
Terence Choong
Resident